Workscope: Medium Voltage Current Carrying Upgrade
- An engineering review will be conducted with the customer and factory in order to determine if an upgrade is possible
| - |
The switchgear cubicle and circuit breaker will be inspected for components needed to complete the upgrade. |
- Before any work is performed, all lock out and tag out procedures will be followed to ensure the equipment is de-energized and safe for maintenance.
- The switchgear cubicle and circuit breaker compartments will be cleaned and inspected for evidence of damaged or defective devices
| - |
The circuit breaker cubicles will be inspected for damaged or missing components. |
| - |
Where applicable, the circuit breakers will be racked in and out to verify proper operation of racking mechanism. |
| - |
Cubicle primary and secondary disconnects will be inspected and cleaned. |
| - |
Cable and bus compartments will be cleaned and inspected. |
| - |
Any item found damaged will be recorded and a suitable replacement identified. |
- As needed, the new components will be installed as per factory specifications
| - |
Modifications to the circuit breaker cubicle will be made according to factory drawings. |
| - |
New bus bracing will be installed in the bus compartment. |
| - |
New bus insulation will be installed as needed. |
| - |
Forced air components will be installed according to factory drawings. |
- Compartment space heaters will be inspected for proper operation.
- Protective interlocks will be checked for proper operation
| - |
Positive, negative and racking interlocks will be checked for proper operation. |
| - |
Circuit breaker interference plates will be checked against the manufacturer's specifications for appropriate location. |
| - |
Any item found damaged will be recorded and a suitable replacement identified. |
- All circuit breaker compartment function positions (disconnect, test and connected) will be checked for proper operation
| - |
The breaker racking mechanism will be racked to all positions and any indicators checked for indication of proper position. |
- The bus insulation will be inspected for evidence of overheating, electrical tracking or weakening of the insulation supports
| - |
All bus compartment covers will be removed as necessary. |
| - |
The bus insulation will be inspected for signs of corona or tracking. |
| - |
The insulation will be cleaned with solvent and rags as applicable. |
| - |
Any item found damaged will be recorded and a suitable replacement identified. |
- Bolted pressure connections will be checked for proper torque (tightness) where possible
| - |
Bolted connections, where accessible, will be checked for proper torque according to applicable standards. |
- Ground bus connections and supports will be checked for proper tightness. Compartment panel door latches will be checked for proper operation
| - |
Compartment door latches will be checked for smooth operation and that doors close completely. |
| - |
For outdoor switchgear, gaskets and outdoor latches will be checked for condition. |
- The circuit breaker elevating/racking mechanism will be cleaned, inspected and lubricated using extended life lubricants
| - |
Jack screws and other racking mechanism components will be checked for proper operation. |
| - |
Where possible, racking mechanism components will be lubricated. |
- All potential transformer and control power transformer compartments will be cleaned and inspected
| - |
All PT and CPT fuse clips and fuse ferrules will be inspected and cleaned. |
- Final electrical tests will be performed, as applicable
| - |
Insulation Resistance Tests - A 500 to 1,000 volt megger will be used to determine the condition of the circuit breaker insulation to the ground and across phases. |
For More Information
Find a service center that performs Switchgear services
Related Information
Request a quote
|